Jal Yukt Shivar
The Government of Maharashtra, Naam Foundation and Tata Motors have signed a MOU to undertake 350 water conservation projects across all districts in Maharashtra. Naam Foundation has been actively involved in addressing water scarcity and mitigating the effects of drought in the state. Our initiatives include the rejuvenation of existing rivers, nalas and other water bodies to enhance their storage capacity, ultimately contributing to the recharge of groundwater table. This collaborative effort aims to ensure sustainable water resources and alleviate the challenges faced by farmers due to water shortages.
Jal Yukt Shivar (Completed Water Bodies)
Sr.No. | District | Block | Village | Funding | Start Date | End Date | Status | Qty. |
1 | Ahmednagar | Parner | Pokhari | Jalnaam | 22-Jan-24 | 31-Jan-24 | Work Completed | 35000 |
2 | Ahmednagar | Nagar | Takali Khatgaon | Galmukt Dharan Galyukt Shivar | 8-Feb-24 | 22-Mar-24 | Work Completed | 68000 |
3 | Ahmednagar | Parner | Kalkup No.1 | Galmukt Dharan Galyukt Shivar | 11-Feb-24 | 20-Mar-24 | Work Completed | 39856 |
4 | Ahmednagar | Parner | Goregaon | Galmukt Dharan Galyukt Shivar (TATA) | 19-Feb-24 | 20-Mar-24 | Work Completed | 32175 |
5 | Ahmednagar | Parner | Mhasobazap No.1 (Harkali) | Galmukt Dharan Galyukt Shivar (TATA) | 1-Mar-24 | 11-Mar-24 | Work Completed | 8100 |
6 | Ahmednagar | Pathrdi | Miri 1 (Khara mala) | Galmukt Dharan Galyukt Shivar | 3-Mar-24 | 1-Apr-24 | Work Completed | 74000 |
7 | Ahmednagar | Parner | Mhasobazap No2. (Haticha Talav) | Galmukt Dharan Galyukt Shivar | 13-Mar-24 | 1-Apr-24 | Work Completed | 30000 |
8 | Ahmednagar | Shrigonda | Mandavgan (Wagh mala) | Galmukt Dharan Galyukt Shivar | 21-Mar-24 | 29-Mar-24 | Work Completed | 11600 |
9 | Ahmednagar | Shevgaon | Mangrul | Galmukt Dharan Galyukt Shivar | 22-Mar-24 | 20-Apr-24 | Work Completed | 30000 |
10 | Ahmednagar | Parner | Jamgaon (biroba) | Galmukt Dharan Galyukt Shivar | 25-Mar-24 | 20-Apr-24 | Work Completed | 70000 |
11 | Ahmednagar | Shrigonda | Mandavgan (Deshmukh mala) | Galmukt Dharan Galyukt Shivar | 30-Mar-24 | 17-Apr-24 | Work Completed | 10000 |
12 | Ahmednagar | Pathrdi | Miri (Shankarwadi) | Galmukt Dharan Galyukt Shivar | 1-Apr-24 | 14-Feb-24 | Work Completed | 74000 |
13 | Ahmednagar | Pathrdi | Pimpalgavan 1 (Panchami Satha Bandhara) | Galmukt Dharan Galyukt Shivar | 2-Apr-24 | 20-Apr-24 | Work Completed | 9000 |
14 | Pune | Ambegaon | Adivare | Tata Motors- C S R | 18-Dec-23 | 10-Feb-24 | Work Completed | 5967 |
15 | Pune | Purandar | Nazre No. 4 | Jalyukt Shivar | 25-Jan-24 | 5-Feb-24 | Work Completed | 25814 |
16 | Pune | Purandar | Nazare 3 | Jalyukt Shivar | 7-Feb-24 | 14-Feb-24 | Work Completed | 25814 |
17 | Pune | Purandar | Nazare 2 | Jalyukt Shivar | 15-Feb-24 | 23-Feb-24 | Work Completed | 25814 |
18 | Pune | Purandar | Nazare 1 | Jalyukt Shivar | 23-Feb-24 | 28-Feb-24 | Work Completed | 23000 |
19 | Pune | Purandar | Tatewadi No 1 | Jalyukt Shivar | 25-Feb-24 | 29-Feb-24 | Work Completed | 22000 |
20 | Pune | Purandar | Borake Mala | Jal Yukta Shivar Yojana | 11-Mar-24 | 11-Mar-24 | Work Completed | 26000 |
21 | Pune | Purandar | Siddheshwar | Jal Yukta Shivar Yojana | 12-Mar-24 | 19-Mar-24 | Work Completed | 34000 |
22 | Pune | Purandar | Tatewadi No 2 | Jalyukt Shivar | 13-Mar-24 | 18-Mar-24 | Work Completed | 24700 |
23 | Pune | Mulshi | Nive | Jalyukt Shivar | 19-Mar-24 | 4-Apr-24 | Work Completed | 30000 |
24 | Satara | Phaltan | Chambhardurg (Jaoli) | Galmukt Dharan Galyukt Shivar | 20-Mar-24 | 21-Apr-24 | Work Completed | 14961 |
25 | Satara | Phaltan | Kodaldara (Jaoli) | Galmukt Dharan Galyukt Shivar | 20-Mar-24 | 21-Apr-24 | Work Completed | 10588 |
26 | Beed | Ashti | Kasari Talav | Galmukt Dharan Galyukt Shivar | 10-Jan-24 | 20-Jan-24 | Work Completed | 17383 |
27 | Thane | Shahapur | Babhale (Bayancha Talav) | Galmukt Dharan Galyukt Shivar | 8-Mar-24 | 11-Mar-24 | Work Completed | 365 |
28 | Thane | Shahapur | Babhale (Maan Talav) | Galmukt Dharan Galyukt Shivar | 11-Mar-23 | 21-Mar-24 | Work Completed | 2917 |
29 | Thane | Shahapur | Babhale (Anusayamata Mandir) | Galmukt Dharan Galyukt Shivar | 23-Mar-24 | 26-Mar-24 | Work Completed | 420 |
30 | Thane | Shahapur | Dolkhamb 1 | Galmukt Dharan Galyukt Shivar | 23-Mar-24 | 30-Mar-24 | Work Completed | 31666 |
31 | Thane | Shahapur | Manjare (PashtePada) | Galmukt Dharan Galyukt Shivar | 23-Mar-24 | 27-Mar-24 | Work Completed | 13700 |
32 | Thane | Shahapur | Pashtepada 2 (Hobacha Tep Chech Tom (PashtePada) | Galmukt Dharan Galyukt Shivar | 27-Mar-24 | 6-Apr-24 | Work Completed | 13700 |
33 | Thane | Shahapur | Nandwal (Dhavdhyacha ShetTalav) | Galmukt Dharan Galyukt Shivar | 27-Mar-24 | 31-Mar-24 | Work Completed | 465 |
34 | Thane | Shahapur | Dolkhamb 2 Bandhanpada | Galmukt Dharan Galyukt Shivar | 31-Mar-24 | 6-Apr-24 | Work Completed | 31666 |
35 | Ahmednagar | Parner | Palve Khurd 1 (Bargal Vasti) | Galmukt Dharan Galyukt Shivar | 4-Apr-24 | 4/13/2024 | Work Completed | 25000 |
36 | Ahmednagar | Parner | Malkup (Mondave Pazar Talav) | Galmukt Dharan Galyukt Shivar | 5-Apr-24 | 4/14/2024 | Work Completed | 13000 |
37 | Ahmednagar | Pathrdi | Pimpalgavan (gav talav) | Galmukt Dharan Galyukt Shivar | 21-Apr-24 | 5/4/2024 | Work Completed | 23625 |
38 | Ahmednagar | Parner | Palve Khurd 1 (shelke mala) | Galmukt Dharan Galyukt Shivar | 8-Mar-24 | 2-Apr-24 | Work Completed | 24375 |
39 | Ahmednagar | Parner | Kalkup No.2 (Bashingacha Talav) | Galmukt Dharan Galyukt Shivar | 21-Mar-24 | 30-Apr-24 | Work Completed | 45000 |
40 | Ahmednagar | Nevasa | Sureshnagar | Galmukt Dharan Galyukt Shivar | 11-Apr-24 | 29-Apr-24 | Work Completed | 5000 |
41 | Ahmednagar | Parner | Walavane (Inam) | Galmukt Dharan Galyukt Shivar | 11-Apr-24 | 29-Apr-24 | Work Completed | 17400 |
42 | Ahmednagar | Nevasa | Sureshnagar | Galmukt Dharan Galyukt Shivar | 18-Apr-24 | 29-Apr-24 | Work Completed | 3900 |
43 | Pune | Ambegaon | Adivare | Tata Motors- C S R | 18-Dec-23 | 29-Dec-23 | Work Completed | 5967 |
44 | Thane | Shahapur | Dolkhamb 3 Bhinar | Galmukt Dharan Galyukt Shivar | 7-Apr-24 | 20-Apr-24 | Work Completed | 31668 |
45 | Thane | Shahapur | Chikhali (Naykacha Talav) | Galmukt Dharan Galyukt Shivar | 7-Apr-24 | 21-Apr-24 | Work Completed | 575 |
46 | Thane | Shahapur | Pashtepada 3 | Galmukt Dharan Galyukt Shivar | 7-Apr-24 | 23-Apr-24 | Work Completed | 13700 |
47 | Thane | Shahapur | Umavanepada | Galmukt Dharan Galyukt Shivar | 24-Apr-24 | 23-Apr-24 | Work Completed | 11875 |
48 | Thane | Shahapur | Sokandepada | Galmukt Dharan Galyukt Shivar | 25-Apr-24 | 23-Apr-24 | Work Completed | 11875 |